Cache Creek Tube Phase 2C

In 2020 Westwood Curtis Construction successfully completed a project for the Town of Jackson, Wyoming that included replacement of aging storm water piping with new 48”, 30”, 24”, 18”and 12” corrugated HDPE piping, 8 additional precast concrete structures were installed as well. Along with the storm sewer, 330 lineal feet (16 feet deep) of 10” PVC sanitary sewer and man holes were replaced. The project was completed in October 2020 totaling $732,000.